BURKE COUNTY, GA (WFXG) -
Another major component has arrived at Georgia
Power's Vogtle 3 and 4 construction
site.
The Unit 3 deaerator was delivered safely on Saturday,
after traveling thousands of miles by land, sea and river from South Korea.
The 300-ton deaerator was off loaded at the Port of
Savannah, and then traveled up the Savannah River by barge to Georgia Power's
Plant McIntosh. From there, it was placed on an oversized transporter for the
two-day, 75-mile trip to the site.
Because of the component's size - 148 feet long, nearly
18 feet wide and 19 feet high - utility trucks were positioned at the front and
rear of the transporter to lift overhead utility lines along the route. Local
law enforcement also provided assistance for traffic control and other
logistical needs.
The deaerator functions like a water purifier,
eliminating dissolved gases, such as carbon dioxide and oxygen, from feedwater
before it gets to a boiler and its pipeline. Deaeration prevents corrosion,
helping to reduce plant maintenance and operating costs.
The Vogtle nuclear energy facility is incorporating
safety and technology enhancements that improve on the already stellar record
of the company's operating facilities. Significant progress continues to be
made at the site. Construction is more than one-third complete, and major
ongoing activities include work on the Unit 3 nuclear island, the containment
vessel assembly, turbine building foundation, cooling tower foundations, raw
water intake structure preparation, switchyard modifications and new transmission
installation.
The construction of Vogtle 3 and 4 is the largest
job-producing project in Georgia, employing approximately 5,000 people during
peak construction and creating 800 permanent jobs when the plant begins
operating. Once complete, the new units will produce enough electricity to
power 500,000 Georgia homes and businesses.
At the site, 750 tons of rebar and 5,800 cubic yards of
concrete for the turbine island have been installed; 3,500 tons of rebar and
20,000 cubic yards of concrete for cooling towers have been installed; and the
heavy lift derrick which is 560 feet tall and one of the largest cranes in the
world, has performed its first lift.